Procedure for obtaining Domestic/Commercial Service Connection
(ii) In case of joint property, certified copies of proof of ownership such as legal heir certificate along with parent documents specified in note (i) above and consent letters from co-owners. If consent letter is not produced, an indemnity bond with enhanced security deposit.
(iii) If the applicant is not the owner, consent letter from owner in Form No. 5 or valid proof of occupancy and indemnity bond in Form No.6.
(iv) As per Division Bench Order dated 23.8.2006, for all special/multistoried buildings in Chennai Metropolitan area, Planning permit from competent authority has to be submitted along with application and Completion Certificate from competent authority has to be submitted before effecting supply.
All Forms are available under forms menu
The intending consumer shall comply any decree or order or judgment of any civil court in regard to the supply of electricity or other requirements mentioned in such decree or order or judgment.