Power Projects

  • HOME
  • Power Projects
Name                         Capacity

Estimate cost   (in Rs.)

Funding Agency Programme of commissioning

    Thermal Power Projects

NCTPS-Stage-II Unit-1 1x600MW 2475 crores(EPC Cost) Financial tie up is made with REC by M/s. BHEL

   

Commercial Operation Declaration on 20.3.2014

NCTPS-Stage-II Unit-2 1x600MW 2211.105 crores(EPC Cost) M/s.REC Commercial Operation Declaration on 08.05.2014

MTPS Stage-III 

1x600MW

3114.71 crores(EPC Cost)

M/s.PFC

Commercial Operation Declaration on 12.10.2013

ENNORE SEZ

Environmental Clearance

Environmental Clearance and Environmental Management Report-For the period ending 30.06.2022

2x660MW 7688 crores M/s PFC The project is expected to be commissioned for   Unit 1 on 31.08.2020 and Unit 2 on 31.10.2020.

ETPS Expansion project

Environmental Clearance

1x660MW 8364.3 crores M/s PFC
The project is expected to be
 commissioned in 2022-23.

NCTPS Stage-III

Environmental Clearance

EC Compliance Report(April-2019 to Sep-2019)

Environmental Clearance(Oct-2019 to March-2020)

Environmental Clearance(April-2020 to September-2020)

Environmental Clearance(October-2020 to March-2021)

Environmental Clearance(April-2021 to
Sep-2021)

Environmental Clearance(October-2021 to
March-2022)

Environmental Clearance And Environmental Management(April-2022 to
October-2022)

1X800MW 6376 crores M/s REC
The project is expected to be
 commissioned in   2019-20.
UPPUR

Environmental Clearance

2X800MW 12,778 crores M/sBHEL(For BTG)
The project is expected to be
 commissioned in  2022-23.
UDANGUDI

Environmental Clearance for Coal Jetty issued on 03.08.2022

2X660MW Rs. 10615 Crores M/s BHEL ( Complete Project) M/s. ITD Cementation India Limited ( Captive Coal Jetty)
The project is expected to be
 commissioned in  2021-2022.

    Hydro Power Projects

Periyar Vaigai 3 SHEP 2X2 MW 75 crores M/s.PFC Unit I & II synchronised on 11-09-2013 &        09-10-2013 respectively
Periyar Vaigai 4 SHEP 2x1.25MW 57.07 crores M/s.PFC Unit-&Unit-II Synchronized on 01.03.2016,29.02.2016respectively
Bhavani Barrage 1 HEP 2x5 MW 185.81 crores TANGEDCO Unit-I&Unit II Synchronized on 29.05.2015,02.07.2015 respectively.
Bhavani Barrage 2 HEP 2x5 MW 187.61 crores TANGEDCO

Unit I & II synchronised on 26.10.2012 &      29-10-2012 respectively.

Kundah pumped storage hydro-electric project (4x125MW)

Environmental Clearance-Kundah pumped storage hydro-electric project (4x125MW)

4x 125MW 1831.29 crores REC

The project is expected to be commissioned on 2022-23.

  Joint Venture Projects

NTPC TNEB Energy Co. Ltd.(NTPC-TNEB joint venture) 3x500 MW 10080.50 crores M/s.REC 29/11/2012        -   unit-1
25/08/2013        -   unit-2
26/02/2015        -   unit-3
NLC Tamil Nadu Power Ltd(NLC- TNEB joint venture) 2x500MW 7293.48 crores Bank of Baroda consortium 18/06/2015      - Unit -1
29/08/2015     -  Unit-2

New Projects- Thermal

New Projects- Hydro