Name | Capacity |
Estimate cost (in Rs.) |
Funding Agency | Programme of commissioning | ||||
Thermal Power Projects |
||||||||
NCTPS-Stage-II Unit-1 | 1x600MW | 2475 crores(EPC Cost) | Financial tie up is made with REC by M/s. BHEL |
Commercial Operation Declaration on 20.3.2014 |
||||
NCTPS-Stage-II Unit-2 | 1x600MW | 2211.105 crores(EPC Cost) | M/s.REC | Commercial Operation Declaration on 08.05.2014 | ||||
1x600MW |
3114.71 crores(EPC Cost) |
M/s.PFC |
Commercial Operation Declaration on 12.10.2013 |
|||||
Environmental Clearance and Environmental Management Report-For the period ending 30.06.2022 |
2x660MW | 7688 crores | M/s PFC | The project is expected to be commissioned for   Unit 1 on 31.08.2020 and Unit 2 on 31.10.2020. | ||||
1x660MW | 8364.3 crores | M/s PFC |
The project is expected to be
commissioned in 2022-23.
|
|||||
EC Compliance Report(April-2019 to Sep-2019) Environmental Clearance(Oct-2019 to March-2020) Environmental Clearance(April-2020 to September-2020) Environmental Clearance(October-2020 to March-2021) Environmental Clearance(April-2021 to Environmental Clearance(October-2021 to Environmental Clearance And Environmental Management(April-2022 to |
1X800MW | 6376 crores | M/s REC |
The project is expected to be
commissioned in 2019-20.
|
||||
UPPUR | 2X800MW | 12,778 crores | M/sBHEL(For BTG) |
The project is expected to be
commissioned in 2022-23.
|
||||
UDANGUDI | 2X660MW | Rs. 10615 Crores | M/s BHEL ( Complete Project) M/s. ITD Cementation India Limited ( Captive Coal Jetty) |
The project is expected to be
commissioned in 2021-2022.
|
||||
Hydro Power Projects |
||||||||
Periyar Vaigai 3 SHEP | 2X2 MW | 75 crores | M/s.PFC | Unit I & II synchronised on 11-09-2013 & 09-10-2013 respectively | ||||
Periyar Vaigai 4 SHEP | 2x1.25MW | 57.07 crores | M/s.PFC | Unit-&Unit-II Synchronized on 01.03.2016,29.02.2016respectively | ||||
Bhavani Barrage 1 HEP | 2x5 MW | 185.81 crores | TANGEDCO | Unit-I&Unit II Synchronized on 29.05.2015,02.07.2015 respectively. | ||||
Bhavani Barrage 2 HEP | 2x5 MW | 187.61 crores | TANGEDCO |
Unit I & II synchronised on 26.10.2012 & 29-10-2012 respectively. |
||||
Kundah pumped storage hydro-electric project (4x125MW)
Environmental Clearance-Kundah pumped storage hydro-electric project (4x125MW) |
4x 125MW | 1831.29 crores | REC |
The project is expected to be commissioned on 2022-23. |
||||
Joint Venture Projects |
||||||||
NTPC TNEB Energy Co. Ltd.(NTPC-TNEB joint venture) | 3x500 MW | 10080.50 crores | M/s.REC | 29/11/2012 - unit-1 25/08/2013 - unit-2 26/02/2015 - unit-3 |
||||
NLC Tamil Nadu Power Ltd(NLC- TNEB joint venture) | 2x500MW | 7293.48 crores | Bank of Baroda consortium | 18/06/2015 - Unit -1 29/08/2015 - Unit-2 |
||||