Hydro Stations

  • HOME
  • Hydro Stations
 

SHOLAYAR POWER HOUSE – I

 

 

·             Source from Sholayar Reservoir

 

·         Net Capacity at FRL (MCFT) is 4800

 

·         Irrigation

 

 

 

 

Salient Features

 

LOCATION

MANOMBOLI

ELEVATION    

1931 FEET

INSTALLED CAPACITY

2 X 35 = 70 MW

No. OF UNIT

2

DATE OF COMMISSIONING

UNIT.1 -  22.04.1971

UNIT.2 - 04.05.1971

 

 

 

 

 

 

 

 

 

 

SHOLAYAR POWER HOUSE – II

 

 

·             Source from Sholayar Reservoir

 

·             Capacity at FRL (in MCFT) is 4800

 

·             Irrigation - Inter state water sharing to Kerala.

 

 

Salient Feature

    

LOCATION

SHOLAYAR P.H. II

ELEVATION    

2750 FEET

INSTALLED CAPACITY

25 MW

No. OF UNIT

1

DATE OF COMMISSIONING

29.03.1971

 

 

 

 

 

 

 

 

 

 

ALIYAR POWER HOUSE

 

 

·             Source from Upper Aliyar Dam

 

·             Net Capacity at FRL (in MCFT) is 914.89

 

·            Non -Irrigation

 

 

 

 

     Salient Features

 

LOCATION

ALIYAR/ Coimbatore

ELEVATION    

1083 FEET

INSTALLED CAPACITY

60 MW

No. OF UNIT

1

DATE OF COMMISSIONING

21.03.1970

 

 

 

 

ALIYAR MINI POWER HOUSE

 

 

 

·             Source from Lower Aliyar Dam

 

·             Source from Net Capacity at FRL (in MCFT) is 3553

 

·             Irrigation

 

 

 

 

   Salient Features

 

LOCATION

ALIYAR/ Coimbatore

ELEVATION    

1083 FEET

INSTALLED CAPACITY

2 X 1.25 MW

No. OF UNIT

2

DATE OF COMMISSIONING

23.09.2002

 

 

 

 

SARKARPATHY POWER HOUSE

 

 

·             Source from Parambikulam, Thunakadavu

 

·             Net Capacity at FRL (in MCFT) is 11820

 

·             Irrigation

 

 

 

Salient Features

 

LOCATION

SARKARPATHY/ Coimbatore

ELEVATION    

1429 FEET

INSTALLED CAPACITY

30 MW

No. OF UNIT

1

DATE OF COMMISSIONING

14.08.1966

 

 

 

 

 

 

 

 

 

 

KADAMPARAI POWER HOUSE (PUMPED STORAGE SCHEME)

   

 

·             Source from Kadamapari Reservoir/Upper Aliyar Dam

 

·             Net Capacity at FRL is 940.38 /737

 

·           Non  Irrigation

 

 

 

  Salient Features

 

LOCATION

KADAMPARAI/. Coimbatore

ELEVATION    

EL 710

INSTALLED CAPACITY

4 X 100 = 400 MW

No. OF UNIT

4

DATE OF COMMISSIONING

UNIT.1- 17.10.1987

UNIT.2-26.02.1988

UNIT.3- 12.04.1989

UNIT.4- 16.12.1988

 

 

 

 

 

 

 

 

 

 

 

Mode of Operation      

Generation Mode – The machines will be operated to cater the Peak hour demand for full load , the generation

will be depending on the kadamparai storage and the level of Upper Aliyar dam.

 Pump Mode: The machines will be operated as pump mode to pump the water from upper Aliyar dam

to kadamparai reservoir during night hours on grid frequency above 49.4 Hz and heavy under drawl of

UI from central pool.

 

THIRUMURTHY MINI PH.

 

 

 

·             Source from Thirumurthy Dam

 

 

·             Irrigation

 

 

 

 

 

 

Salient Features

 

LOCATION                   

Udumalpet

INSTALLED CAPACITY   

3 X 0.65 MW

No. OF UNIT

3

DATE OF COMMISSIONING

UNIT.1- 20.03.2000

UNIT.2- 20.03.2000

UNIT.3- 20.03.2000

 

 

 

 

 

 

 

 

 

POONACHI MINI PH

 

 

 

·           Source from Punachi river - Run of River

 

·             Non Irrigation

 

 

 

  Salient Features

 

LOCATION            

Poonachi/Coimbatore District

INSTALLED CAPACITY

2 X 1 MW

No. OF UNIT

2

DATE OF COMMISSIONING

UNIT.1- 12.11.1992

UNIT.2- 16.12.1992

 

 

 

 

 

 

     

 

AMARAVATHI

 

 

·             Source from Amaravathy

 

·             Source from Net Capacity at FRL(MCFT) -3749

 

·             Irrigation

 

 

 

 

Salient Features

 

LOCATION         

Coimbatore District

INSTALLED CAPACITY

2 X 2 MW

No. OF UNIT

2

DATE OF COMMISSIONING

UNIT.1- 21.09.2006

UNIT.2- 30.11.2006

 

 

 

 

 

     

 

   

© 2017 TANGEDCO