Home | About  Us |  Consumer Info |  Billing Services |  Procurement |  HRD & Research |  Reach Us |  Site map

****General instruction to Public regarding effecting of electricity service connections within a day to the Domestic and Commercial buildings           ****KIND ATTENTION LT ELECTRICTY CONSUMERS-Make payment of LT Electricity Bills only through TANGEDCO Section Office Counters/E-seva centers of GoTN/Post Offices/Branch Counters of 3 banks viz., City Union Bank(CUB), Lakshmi Vilas Bank (LVB) and Tamilnad Mercantile Bank (TMB). Also through ATM of TMB. Online payment only through www.tangedco.gov.in. Payments not to be made through unauthorised agent/Website so as to avoid disconnection of electricity supply for non-payment of EB Bills”.           For Power Failure in Chennai city - Contact: 1912 for BSNL users, 0441912 for non-BSNL users          

          Tamil Nadu State Solar Energy policy has been announced by Hon’ble Chief Minister of Tamil Nadu on 20.10.12. In the policy it is proposed to establish solar PV power plants for a capacity of 3000 MW within next 3 years as detailed below:

 

PHASE

(2013-2015)

TARGET

(MW)

2013

1000

2014

1000

2015

1000

TOTAL ( By 2015)

3000

 

The 3000 MW of solar power generation will be achieved through Utility Scale Projects, Roof tops and REC mechanism.

 

The Solar Energy Policy mandates 6% Solar Purchase Obligation (SPO) (starting with 3% till December 2013 & 6% from January 2014) for the HT consumers (HT Tariff I to V) and LT commercial consumers.

 

In order to facilitate developers to establish Solar Power Plants of capacity 1 MW and above, TANGEDCO proposes to facilitate the investors by procuring the energy generated from these plants through a long term power purchase agreement up to a total capacity of 1000 MW. The developers will be selected through the competitive bidding process.

Tamil Nadu solar energy policy 2012

Solar power evacuation capacity

Solar irradiance data in Tamil Nadu

 

TANGEDCO