****KIND ATTENTION LT ELECTRICTY CONSUMERS-Make payment of LT Electricity Bills only through TANGEDCO Section Office Counters/E-seva centers of GoTN/Post Offices/Branch Counters of 3 banks viz., City Union Bank(CUB), Lakshmi Vilas Bank (LVB) and Tamilnad Mercantile Bank (TMB). Also through ATM of TMB. Online payment only through www.tangedco.gov.in. Payments not to be made through unauthorised agent/Website so as to avoid disconnection of electricity supply for non-payment of EB Bills”.           ** Online application filing facility for New Low Tension Service Connection inaugurated on 05.08.2016 by the Honourable Chief Minister, Govt of Tamil Nadu **           For Power Failure in Chennai city - Contact: 1912 for BSNL users, 0441912 for non-BSNL users          

Vallur Thermal Power Project
 
Location
:
Vallur village in North Chennai
 
Capacity
:
3 x 500MW
 
Total cost of the project
:
Rs 10080.50 Crores
 
Name of the contractor
:
Main plant contractor M/s.
M/s.Bharat  Heavy Electrical Limited.
 
Zero date
:
Stage.I – 13.08.2007 
Stage.II – 28.07.2009 
 
 
Schedule date of commissioning
:
Unit I  - October 2010
Unit II - March 2011
Unit III - September 2012
 
Present stage of the project
:
UNIT I:
  • Synchronization completed on  09.03.2012.
  • All works in Ash Handling and coal handling system completed and put in service.
  • The coal conveyor system includes the newly commissioned 4.4 Kms long pipe conveyor with a capacity of 4000 tonnes /hour -making it the world's largest pipe conveyor.
  • The unit declared on Commercial operation from 00.00 Hrs. on 29.11.2012.

 UNIT II:

  • Boiler Light up completed on 16.07.2012.
  • Turbine Box Up completed.
  • Steam blowing first stage completed on 02.12.2012.
  • Unit Synchronised on 26.02.2013.
  • The unit declared on Commercial operation from 00.00 Hrs. on 25.08.2013.

 UNIT III:

  • Boiler Hydro test completed on 30.09.2012.
  • Boiler Light up completed on 31.08.2013.
  • Generator Stator arrived at site.
  • TG box up completed. 
  • Unit Synchronised on 28.02.2014.
  • The unit declared on Commercial operation from 00.00 Hrs. on 26.02.2015.

 