|
|
Location
|
:
|
Vallur village in North Chennai
|
|
|
Capacity
|
:
|
3 x 500MW
|
|
|
Total cost of the project without IDC
|
:
|
Stage.I : 2 x 500MW : Rs.5424 crore
Stage.II : 1x500MW : Rs.3020 crore
----------------
Total : Rs.8444 crore
|
|
|
Name of the contractor
|
:
|
Main plant contractor M/s.
M/s.Bharat Heavy Electrical Limited.
|
|
|
Zero date
|
:
|
Stage.I – 13.08.2007
Stage.II – 28.07.2009
|
|
|
Schedule date of commissioning
|
:
|
Unit I - October 2010
Unit II - March 2011 Unit III - September 2012
|
|
|
Present stage of the project
|
:
|
UNIT I:
- Synchronization completed on 09.03.2012.
- All works in Ash Handling and coal handling system completed and put in service.
- The coal conveyor system includes the newly commissioned 4.4 Kms long pipe conveyor with a capacity of 4000 tonnes /hour -making it the world's largest pipe conveyor.
- The unit declared on Commercial operation from 00.00 Hrs. on 29.11.2012.
UNIT II:
- Boiler Light up completed on 16.07.2012.
- Turbine Box Up completed.
- Steam blowing first stage completed on 02.12.2012.
- Unit Synchronised on 26.02.2013.
- COD is expected in May 2013.
UNIT III:
- Boiler Hydro test completed on 30.09.2012.
- Boiler Light up anticipated in June 2013.
- Generator Stator arrived at site.
- TG box up anticipated in August 2013
- Synchronization anticipated in October 2013.
|